Schedule performance at the planned go-live
At 31 March 2025 (the planned go-live of ERP-RET): planned value of each task = BaselineBudget x share of the planned window elapsed (0-1, linear between PlannedStart and PlannedFinish); earned value = BaselineBudget x share of the actual window elapsed (ActualStart to ActualFinish). SPI = total earned value / total planned value for the project. What was it, to 4 decimals?