Commissioned, then the customer left

EXP-JA-L4 was built for Mizan Manufacturing's largest customer, which stopped buying on 1 April 2025 (DD-BVA-001). How many days passed from the "Commissioning complete" milestone's ActualDate to 1 April 2025?
Expected
One whole number · KPI card
Tables
FactMilestone · columns
  • FactMilestone
  • MilestoneName
  • ActualDate