Billed ahead of progress
On the client project MOB-CUS0061, revenue earned to a date = contract value (sum of BillingAmount) x project % complete (earned value / OriginalBudget at the month end). At 31 March 2024 (the month end after milestone M2 was invoiced), what was billed to date minus revenue earned - the over-billing - in USD?
- Expected
- One amount in USD, 2 decimals · KPI card
- Tables
-
FactMilestone, FactProgress, DimTask, DimProject · columns