DD-PRJ-003-Q043 Very Hard Time series

Estimate at completion of ERP-MFG at its planned go-live

At 30 September 2025 (ERP-MFG's planned finish), EAC = BAC / CPI where BAC = OriginalBudget and CPI = earned value / actual cost to date. What was it, in USD?
Expected
One amount in USD, 2 decimals · KPI card
Tables
FactProgress, FactCost, FactTimesheet, DimResource +1 · columns
  • FactProgress
  • FactCost
  • FactTimesheet
  • DimResource
  • DimProject
  • PostingDate
  • WorkDate
  • Amount
  • Hours
  • HourlyRate
  • PercentComplete
  • OriginalBudget