Estimate at completion of ERP-MFG at its planned go-live
At 30 September 2025 (ERP-MFG's planned finish), EAC = BAC / CPI where BAC = OriginalBudget and CPI = earned value / actual cost to date. What was it, in USD?
- Expected
- One amount in USD, 2 decimals · KPI card
- Tables
-
FactProgress, FactCost, FactTimesheet, DimResource +1 · columns